OBJECTIVE 1.1 To lay down a procedure for Preventive Maintenance of Air compressor & Dryer 2. RESPONSIBILITY Assistant Engineering - To Follow the SOP Executive Engineering - To comply the SOP 3. PROCEDURE 3.1 WEEKLY MAINTENANCE Clean the air intake filter with compressed air Check and ensure the air compressor load is below 20 Amps during … Continue reading Preventive Maintenance of Air compressor & Dryer
Category: Uncategorized
Preventive Maintenance of Tablet Compression Machine
OBJECTIVE To lay down a procedure for Preventive Maintenance of Tablet Compression Machine RESPONSIBILITY Assistant - Engineering - To follow the SOP Executive - Engineering - To Comply the SOP PROCEDURE Weekly maintenance Check the machine rotation with hand wheel, it should rotate freely. Check the hydraulic oil, gearbox oil levels, should be 3/4th of the … Continue reading Preventive Maintenance of Tablet Compression Machine
Preventive Maintenance of Blister Packing Machine
OBJECTIVE To lay down a procedure for Preventive Maintenance of Blister packing machine 230 XT, TR-100L. 2. RESPONSIBILITY Assistant - Engineering &Production - To follow the SOP Executive - Engineering &Production - To Comply the SOP 3. PROCEDURE Weekly Maintenance Check all the movable parts for proper lubrication. Lubricate the Punching tool ball case, Embossing unit, platen … Continue reading Preventive Maintenance of Blister Packing Machine
Preventive Maintenance of Fluid Bed Drier
OBJECTIVE 1.1 To lay down a procedure for Preventive Maintenance of Fluid Bed Drier-20Kgs, 120Kgs. RESPONSIBILITY Assistant - Engineering - To follow the SOP Executive - Engineering - To Comply the SOP PROCEDURE Weekly Maintenance Check the pneumatic cylinders and solenoid valves for proper working condition. Check earthing bracket plungers for proper working, if required … Continue reading Preventive Maintenance of Fluid Bed Drier
Preventive Maintenance of Automatic Capsule Filling
OBJECTIVE To lay down a procedure for Preventive Maintenance of Automatic capsule filling line AF-40T, AF-90T, And AF-150T. 2. RESPONSIBILITY Assistant - Engineering - To follow the SOP Executive - Engineering - To Comply the SOP 3. PROCEDURE Weekly Maintenance Check the oil level in the vacuum pump through view glass and refill the oil if … Continue reading Preventive Maintenance of Automatic Capsule Filling
Preventive Maintenance of Rapid Mixer Granulator
OBJECTIVE To lay down a procedure for Preventive Maintenance of Rapid Mixer Granulator-25, 250, 300Ltrs. 2. RESPONSIBILITY Assistant – Engineering - to follow the SOP Executive –Engineering - to comply the SOP 3. PROCEDURE Weekly Maintenance Check the lubrication oil in the FRL unit and if required top up with specified lubricant. Check the oil … Continue reading Preventive Maintenance of Rapid Mixer Granulator
Preventive Maintenance of Octagonal Blender
OBJECTIVE To lay down the procedure for Preventive Maintenance of Octagonal blender 300, 500, 1000, 1500, 2250 Ltrs. 2. RESPONSIBILITY Assistant – Engineering - To follow the SOP Executive – Engineering - To comply the SOP 3. PROCEDURE Monthly Maintenance Check the plumber block housing bolts, if required tight the bolts. Check the gearbox and … Continue reading Preventive Maintenance of Octagonal Blender
Preventive Maintenance of Multi Mill.
OBJECTIVE 1.1 To lay down the procedure for Preventive Maintenance of Multi Mill. RESPONSIBILITY Assistant - Engineering - To follow the SOP Executive - Engineering - To Comply the SOP PROCEDURE Monthly Maintenance Check all the fastenings of the unit, if required tight all the fastenings. Check the miller shaft roller bearings, if required clean … Continue reading Preventive Maintenance of Multi Mill.
Preventive Maintenance of Vibro Sifter
OBJECTIVE To lay down a procedure for Preventive Maintenance of Vibro Sifter - 12”, 30”. 2.0 RESPONSIBILITY Assistant – Engineering - To follow the SOP Executive – Engineering - To comply the SOP 3.0 PROCEDURE Monthly Maintenance Check the hopper supporting compression springs for tension and balancing of the hopper. Check the motor amps and … Continue reading Preventive Maintenance of Vibro Sifter
Sampling and Release of Semi finished Product
SAMPLING OF SEMIFINISHED PRODUCT Samples collected during granulation or blending stage for solid oral dosage forms shall be considered as semi finished product samples.As per BPRR at the end of the each activity, production executive shall issue “SAMPLE TEST REQUEST FORM” to IPQA personnel. IPQA personnel shall sample and submit all samples to the QC … Continue reading Sampling and Release of Semi finished Product